April 26, 2022Asheville City Council
From the minutes, not yet reviewedWhat it does
Lets the City Manager execute a Contract Amendment with Moore & Son Site Contractors for the forest hill/caledonia road Stormwater improvement project.
- Passed with the routine items, in one vote, without discussion.
- What the minutes say it will do: “This project was funded with 2016 General Obligation (GO) bond funds, Stormwater capital funds, and General capital funds.”
- The money, in the minutes' words: “Additional asphalt was required to create a proper crown on the roadway to help direct stormwater to new inlets; this over-run in asphalt needed to complete the project created a budget shortfall in the amount of $37,081.00.”
Official title: Resolution authorizing the City Manager to execute a Contract Amendment with Moore & Son Site Contractors for the forest hill/caledonia road Stormwater improvement project
Carried unanimously, as part of the consent agenda
From the minutes: This motion was seconded by Councilwoman Kilgore and carried unanimously.
Read the motion as recorded
“RESOLUTION NO. 22-77 - RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE A CONTRACT AMENDMENT WITH MOORE & SON SITE CONTRACTORS FOR THE FOREST HILL/CALEDONIA ROAD STORMWATER IMPROVEMENT PROJECT”
Open the minutesConsent agenda, item J